Integrated machinery lines · Lifecycle phase

Commissioning the line: from machine acceptance to handover

Commissioning is where six accepted machines become one working line. This page shows the steps of the phase on RL-1, who is responsible for each, what each step must deliver and when the next one may start — so that the line’s documentation is complete when the line is handed over.

Page context

Line
Reference line RL-1: end-of-line packaging (RL-1)
Stations
Infeed and accumulation conveyor → Filler and capper → Labeler → Inspection and reject → Case packer → Palletizer and stretch wrapper
Lifecycle phase
Commissioning and acceptance
For
System integrators, Safety engineers, Technical writers
Page type
Lifecycle phase — Shows one phase: steps, roles and deliverables
Line map of the reference line · RL-1
  1. Z1 · Filling

    1. Infeed and accumulation conveyorSystem integrator
    2. Filler and capperSupplier A
  2. Z2 · Labeling and inspection

    1. LabelerSupplier B
    2. Inspection and rejectSupplier B
  3. Z3 · Case packing

    1. Case packerSupplier C
  4. Z4 · Palletizing

    1. Palletizer and stretch wrapperSupplier D
  1. Factory acceptance per machine

    Responsible: Each supplier, with the integrator

    Activities

    • Test each machine at the supplier’s site against its specification
    • Test the line interface with a simulated line controller

    Deliverables

    • FAT report per machine
    • Machine technical documentation and instructions
    • Interface test record

    Next step may start when: Each machine passes its FAT; open points have an owner and a date.

  2. Virtual commissioning of the line control

    Responsible: System integrator

    Activities

    • Run the line controller against a simulation model of RL-1
    • Test start, stop and restart sequences and buffer behavior

    Deliverables

    • Tested line control software
    • Updated signal list

    Next step may start when: All sequences in the test plan run in the simulation.

  3. Installation and integration on site

    Responsible: System integrator and suppliers

    Activities

    • Set up and connect the machines and conveyors
    • Test every signal in the signal list end to end
    • Commission the safety controller zone by zone

    Deliverables

    • I/O and signal check records
    • As-built electrical documentation

    Next step may start when: Every signal is tested; each zone stops and resets as specified.

  4. Validation of the safety functions

    Responsible: Safety engineer (integrator)

    Activities

    • Validate each safety function of the line against the safety concept
    • Check the line risk assessment against the built line, including interaction hazards

    Deliverables

    • Validation report
    • Updated line risk assessment and residual risk information

    Next step may start when: All safety functions are validated; residual risks are covered in the instructions for use.

  5. Site acceptance and handover

    Responsible: Operating company and integrator

    Activities

    • Run the line at rated output over the agreed period
    • Train operators and maintenance with the line instructions

    Deliverables

    • SAT report
    • Line technical file, declaration of conformity and instructions for use
    • Training records

    Next step may start when: The operating company accepts the line; the documents are handed over.

Documents at handover: who writes what
DocumentLevelWritten byUsed on these pages
Machine instructions for useMachineEach supplierLinked from task and troubleshooting pages
Line instructions for useLineIntegrator (technical writing)Task, troubleshooting and reference pages
Line risk assessmentLineIntegrator (safety engineering)Safety messages on task pages
Signal list and interface specificationLineIntegrator (automation)Interfaces and signals
Technical file and declaration of conformityLineIntegrator as manufacturer of the assemblyWhen a line becomes one machine

Documentation runs alongside, not after

Line documentation that starts at handover is written from memory. On RL-1 the technical writer joins at virtual commissioning: the start and restart sequences tested there become the restart procedure, the signal tests feed the interface reference, and every open point from the tests is checked for its effect on the instructions. The validation of the safety functions is the last check that the safety messages match the line as built.

knowledge.aitechdoc.world · Reviewed September 26, 2026

RL-1 is a fictional reference line. These pages show how documentation for an integrated machinery line can be structured; they don’t replace the instructions for use of a real line.